Electrical Load Schedule Calculator

Build a proper load schedule the way it appears on a design drawing. List your lights, sockets, motors, HVAC, cookers, water heaters and other loads — each with its quantity, unit rating, power factor and diversity — and the calculator returns the connected load, the diversified maximum demand, a balanced allocation across the three phases, and a recommended incomer rating from standard breaker sizes.

Once you have the incomer current, size its cable with the Cable Sizing and Voltage Drop Calculator.

SheetCALC-03
TitleElectrical Load Schedule Calculator
BasisIET OSG diversity
Rev2026-07
Three-phase rows are ignored on a single-phase supply check.
Kenya nominal: 230 V (line-to-line 400 V).
Headroom for future load growth.
DescriptionCategoryQtyUnit load (W) PFDiversityPhases

Load summary CALC-03 · REV 2026-07

Connected load
Diversified load (maximum demand)
Overall diversity factor
Maximum demand current
Incomer required incl. spare capacity
Recommended incomer
Spare capacity at recommended rating
PhaseDemand (VA)Current (A)
L1
L2
L3
Imbalance

Guidance tool only. Diversity is a matter of engineering judgement — the defaults follow IET On-Site Guide practice but every factor is editable and the final assessment, protective-device coordination and KPLC connection application must be confirmed by a registered engineer.

How this calculator works

  1. Connected load. Each row contributes quantity × unit rating in watts, converted to VA through its power factor. Defaults per category are typical values and fully editable.
  2. Diversity. Not everything runs at once. Each row carries a diversity factor — defaults follow IET On-Site Guide practice (lighting 0.90, sockets 0.40, motors 0.80, HVAC 0.80, cookers 0.60, water heaters 1.00, other 0.80), simplified to a single multiplier. The diversified total is the maximum demand.
  3. Phase allocation. On a three-phase supply, balanced three-phase loads (motors, larger HVAC) contribute one third to each phase; single-phase loads are then packed largest-first onto the least-loaded phase. The table reports VA and amperes per phase and the resulting imbalance, flagging anything above 15%.
  4. Recommended incomer. The worst-phase current (or the total, on single phase) is increased by your chosen spare-capacity allowance — 25% is a common design margin — and matched to the next standard breaker rating (32–1600 A). Above 1600 A the tool refers you to transformer and HV intake design.

Assumptions and limits

  • Diversity is engineering judgement, not law — a hospital theatre and a student hostel with the same connected load deserve different factors. Edit them per row for your building type.
  • Voltages assume the Kenyan LV system, 230/400 V, with the phase voltage editable.
  • Demand above about 60 A on single phase, or 100 A per phase on three phase, triggers advisory notes on supply upgrade and KPLC CT metering.
  • The tool does not perform protective-device discrimination, fault-level or earthing calculations — all part of a full design.

Need a stamped, submission-ready design or a KPLC connection application? See our consultancy services, browse the design document library, or learn the method yourself in a training program.

Share This